Winter concreting · low-carbon

Winter.

Low-carbon pours,
even when it freezes.

We have been keeping concrete at temperature since 1956. Low-carbon cement is slow in the cold. We measure in wall and slab and determine the maturity; our partner Verboom Installatietechniek supplies the heat. Off as soon as your target is reached.

CO₂ per m³ of concreteBinder · 340 kg cement
↓ Less than half the CO₂Cradle to gate26
The film · 0:43

One winter night, from pouring to striking.

Why it matters now

Low-carbon cement is slow in the cold. So construction falls back on Portland cement in winter.

In the Netherlands, blast furnace cement (CEM III) is the usual cement: 55 to 60 percent of what is poured.3 It produces less heat than Portland cement, and at 20 °C it has about a third of the strength after two days.1 At 5 °C the difference grows, because such a cement hardly heats itself.

And so in winter people fall back on clinker-rich cement. Supplier advice says it literally: in frost, “Portland instead of blast furnace”.4 How often that happens has not been measured anywhere. But every time it costs about 200 kg of extra CO₂ per cubic metre.2

That question is growing. Clients put CO₂ limits in the specification, and the new binders are often even slower or more sensitive to temperature.

30–40 %
Less heat than CEM I,
after 7 days at 20 °C1
±⅓
Of the strength of CEM I,
after 2 days at 20 °C1
±200 kg
Extra CO₂ per m³ when
falling back to CEM I2
55–60 %
Share of blast furnace cement
in the Netherlands3
A little heat

With low-carbon cement, a little heat goes further.

Blast furnace cement is more sensitive to temperature than Portland cement. In the cold that is its weakness; with heat it is its strength.

From 5 to 20 °C: this much more maturity per hour5
×3,1CEM III/B
blast furnace cement
×2,4CEM I
Portland cement

So every hour of heat gives more maturity with blast furnace cement than with Portland cement. That is why targeted additional heating works especially well with low-carbon cement.

A low-carbon cement such as CEM III/B, with targeted additional heating, still emits less than half the CO₂ per cubic metre of concrete of regular CEM I.

Additional heating costs 1 to 50 kg of CO₂ per cubic metre; the difference in cement is well over 200 kg.6 Only an open tent heated for days on end comes close to that difference. Hence: targeted, measured, and off at the target.

How it works · heated tunnel formwork

Heat until the target, not by the clock.

Tunnel formwork construction runs on a daily cycle: pour in the afternoon, strike the formwork the next morning. In the cold, that only works with low-carbon cement if you add heat.

Drawing of heated tunnel formwork construction at night and −2 °C: three tunnels under a fresh slab, closed off with sheets and heaters inside. A Sensorbox measures in slab, wall and edge; the Verboom Platform switches the heaters off at the target via the relay on the gas control cabinet. On the phone, the curves run towards the striking limit.
Illustration. The LED tower is an option. Click the products in the drawing
  1. Pour

    In the afternoon, walls and slab are poured in one go. The tunnels are closed off at both ends with sheets, the slab goes under insulation blankets.7

  2. Measure in wall and slab

    The Sensorbox measures in the slab, the wall and the slab edge: where it is coldest and where it matters.

  3. Heat at night

    The tunnel formwork heaters of our partner Verboom Installatietechniek heat the formwork, and with it the wall and slab.

  4. Off at the target

    The platform determines the maturity and, via the relay on their gas control cabinet, switches the heaters off as soon as the striking strength is reached.

  5. Strike in the morning

    Strike the formwork on time, with a report per pour that shows how the concrete developed.

Why measure

Additional heating without measuring is guesswork.

And guesswork goes wrong in three ways. The answer is the same every time: measure in core and edge, determine the maturity, and switch off at the target.

  • Too littleThe strength does not come in time, or people still reach for Portland cement.
  • Too muchAbove 65–70 °C in the core, the concrete risks damage. Too large a difference between core and edge causes cracking. That is why we measure both.
  • Too longHeating on after the target. The only scenario in which the CO₂ advantage disappears.
A red Sensorbox hangs on orange tunnel formwork on site, with a blue measuring cable.
The Sensorbox on tunnel formwork on site.
Partner

For heating, we work together with Verboom Installatietechniek.

Verboom started heating concrete in 1956. Since around 2021, that has been a fully independent company: Verboom Installatietechniek, part of Robogas, with its own owner and separate from Verboom Concrete Technology. They are our partner for heat on the construction site. We measure, they heat, and our systems are matched to each other.

Their speciality is heated tunnel formwork construction: tunnel formwork heaters in the tunnels, gas control cabinets, hoses and the propane tank, including the notification to the environmental authority. They install the complete installation and always do a test firing first.

Our sensors measure in the concrete; the Verboom Platform determines the maturity and switches the heaters off as soon as the striking strength is reached in time. That way you heat no longer than necessary. Need heating to keep work going, or for the site cabin? You can go to them for that too.

Who it is for

One winter pour, four people who want to know.

Client

You can meet your CO₂ requirement with a winter pour too.

Low-carbon cement, with targeted heating, measured and reported.

Site manager

No falling back on Portland cement when it freezes.

You pour CEM III/B. Our partner supplies the heat; we measure and switch the heaters off at the target.

Concrete plant

Your low-carbon mix does not have to come off the list in winter.

The platform calculates with the calibration curve of your mix.

Structural engineer

Core and edge measured, the temperature monitored.

And the report shows how it went.

A calibration curve per mix

The platform calculates using the maturity method (NEN 5970), with the calibration curve from the PDF of your concrete plant. If a new binder comes along, the producer draws up a calibration curve and the platform follows it. That makes it suitable for any mix for which a calibration curve has been drawn up.

Measuring conductivity Under research

Some new binders often barely warm up, and then the temperature shows little. That is why the first tests with measuring conductivity are running.

Winter concreting

Plan your winter pour.

Measuring and determining the maturity is done by Verboom. The heat comes from our partner Verboom Installatietechniek, an independent company. Call either one; we coordinate it together.

Sources

  1. ENCI, Warmteontwikkeling van cement en beton, 2001; ENCI, product sheet CEM III/B 42,5 N-LH/SR IJmuiden, 2020; Heidelberg Materials Nederland, 2024.
  2. Heidelberg Materials Nederland, HM NL bouwt aan een beter milieu, 2024: CO₂ per m³ per cement type; converted to 340 kg of binder per m³, cradle to gate.
  3. SGS INTRON for Rijkswaterstaat, cement use in the Netherlands, 2021.
  4. Supplier advice on pouring concrete in frost (Belgium, 2024); podcast Beton & Staalbouw, August 2026.
  5. Own calculation with the maturity formula of NEN 5970 (weighted maturity according to De Vree).
  6. Own calculation using public reference values: heat per m³ for a covered slab or heated formwork 10–40 kWh, CO₂ per kWh of heat from natural gas 0.27 kg.
  7. Betonhuis, Warme en koude gietbouw.